Medium Voltage Electricity Installation | Instalacion Energia Electrica de Media Tension
During this week, excavation work for the medium voltage electricity installation which will feed the LSST Base Facility and Data Center will begin.
This activity, which is estimated to take 30 days, will start with the tracing of the excavations to continue with the installation of 2 poles in the exterior of the mutliple use court, in the south west area for measuring equipment and reclosers, to then continue with the underground channeling on the south side of the Recinto's perimetral fence, reaching the technical platform which will be built next to the Modulux.