Medium Voltage Electricity Installation | Instalacion Energia Electrica de Media Tension

Thursday, 31 August 2017 - 6:45am

During this week, excavation work for the medium voltage electricity installation which will feed the LSST Base Facility and Data Center will begin. 

This activity, which is estimated to take 30 days, will start with the tracing of the excavations to continue with the installation of 2 poles in the exterior of the mutliple use court, in the south west area for measuring equipment and reclosers, to then continue with the underground channeling on the south side of the Recinto's perimetral fence, reaching the technical platform which will be built next to the Modulux.


Durante esta semana iniciaran los trabajos para la excavación de la instalación eléctrica de media tensión que alimentará el LSST Base Facility y Data Center. 

Esta actividad, que tiene estimada una duracion de 30 dias, comenzará con el trazado de las excavaciones para continuar con la instalación de dos postes en el exterior de la multicancha, en el sector sur poniente para el equipo de medida y reconectadores, para luego continuar con la canalización subterránea por el costado sur de la reja perimetral del Recinto, hasta llegar a la plataforma técnica que será construida a continuación del edificio Modulux.