Timeline

Updated on March, 2017

The project has been divided into two phases: 

Phase 1 ~ April 2017 - September 2018 

Remodeling of the existing building and site clearing/preparation work for the additions.

  • Remodeling of existing office/lab building
  • New air conditioning and heating
  • Remodeling of bathrooms and entries for accesibility
  • Relocation of warehouse building
  • Removal of motel building

Phase 2 ~ June 2017 - June 2018

Construction of the office addition, data center and a common reception/gallery space. 

The physical and operational requirements for all these additions and modifications are defined an AE Design Requirements Document. The AE design has been directed by a Base Facility Development Committee with LSST, AURA and NOAO-S membership.


Actualizado Marzo, 2017

El proyecto ha sido dividido en dos fases:

Fase 1 ~  Abril 2017- Septiembre 2018

Remodelación del edificio existente y trabajo de preparación del sitio para adiciones.

  • Remodelación del edificio/laboratorio existente
  • Aire acondicionado y calefacción nueva
  • Remodelación de baños y entradas con accesibilidad
  • Reubicación de la bodega
  • Eliminación del motel

Fase 2 ~ Junio 2017 – Junio 2018

Construcción de la adición de oficinas, centro de datos y espacio común de recepción/galería.

Los requerimientos físicos y operacionales para todas estas adiciones y modificaciones son definidos como un Documento de Requerimientos de Diseño AE. El diseño AE ha sido dirigido por el Comité de Desarrollo de las Instalaciones Base con membresía de LSST, AURA y NOAO.