Plan for the week of November 14 | Plan para la semana del 14 de Noviembre

2016 Nov 11 - 12:30pm

November 14, 15 

  • Work site installation.
  • Machinery arrival to the site.

November 15, 16, 17, 18 

  • Site preparation and escarpment.
  • Layout and leveling.
  • Excavations.  

November 22, 23, 24, 25

  • Filling and compacting.
  • Watering of the ground.
  • Gravel bed placement.

November 28, 29

  • Parking demarcation.
  • Clearing and work hand over.

NOTE: This work is considered to be done from Monday to Friday from 08:30 am to 5:30 pm.

Fire fighting network | Red contra incendios

2016 Nov 10 - 6:00am

For precaution, the fire fighting network in the tree cutting area will be offline for approximately 2 hours starting at 10:30am. The fire hydrant in the area will be availabe in case of emergency.


Por precaucion, la red contra incendio en el area de tala de arboles, no estara disponible por 2 horas aproximadamente a partir de las 10:30. El grifo que se encuentra en el sector esta habilitado en caso de emergencia.