Plan for the week of November 14 | Plan para la semana del 14 de Noviembre
November 14, 15
- Work site installation.
- Machinery arrival to the site.
November 15, 16, 17, 18
- Site preparation and escarpment.
- Layout and leveling.
- Excavations.
November 22, 23, 24, 25
- Filling and compacting.
- Watering of the ground.
- Gravel bed placement.
November 28, 29
- Parking demarcation.
- Clearing and work hand over.
NOTE: This work is considered to be done from Monday to Friday from 08:30 am to 5:30 pm.
Fire fighting network | Red contra incendios
For precaution, the fire fighting network in the tree cutting area will be offline for approximately 2 hours starting at 10:30am. The fire hydrant in the area will be availabe in case of emergency.
Por precaucion, la red contra incendio en el area de tala de arboles, no estara disponible por 2 horas aproximadamente a partir de las 10:30. El grifo que se encuentra en el sector esta habilitado en caso de emergencia.
Programmed water cut-off | Corte de agua programado
Today, water cut-off has been programmed at 5:30pm for one hour. This will affect the cientific building and house 6.