Plan for the week of November 14 | Plan para la semana del 14 de Noviembre

Friday, 11 November 2016 - 12:30pm

November 14, 15 

  • Work site installation.
  • Machinery arrival to the site.

November 15, 16, 17, 18 

  • Site preparation and escarpment.
  • Layout and leveling.
  • Excavations.  

November 22, 23, 24, 25

  • Filling and compacting.
  • Watering of the ground.
  • Gravel bed placement.

November 28, 29

  • Parking demarcation.
  • Clearing and work hand over.

NOTE: This work is considered to be done from Monday to Friday from 08:30 am to 5:30 pm.

Any extra activities or delays due to eventualities will be reported opportunely.


Noviembre 14, 15 

  • Instalación de Faenas.
  • Traslado de maquinaria al sector de trabajos.

Noviembre 15, 16, 17, 18 

  • Preparación del Terreno y Escarpe.
  • Trazado y Niveles.
  • Excavaciones  

Noviembre 22, 23, 24, 25

  • Relleno y compactado.
  • Riegos de terreno.
  • Aplicación de cama de gravilla.

Noviembre 28, 29 

  • Demarcación de estacionamientos.
  • Aseo y entrega.

NOTA: Los trabajos están considerados realizarlos de lunes a viernes en los horarios normales de oficina esto es de 08:30 a 17:30 Hrs.

Cualquier actividad extra o atrasos por imprevistos será avisado oportunamente.


Noviembre 14, 15 

  • Instalación de Faenas.
  • Traslado de maquinaria al sector de trabajos

Noviembre 15, 16, 17, 18 

  • Preparación del Terreno y Escarpe.
  • Trazado y Niveles.
  • Excavaciones  

Noviembre 22, 23, 24, 25

  • Relleno y compactado.
  • Riegos de terreno.
  • Aplicación de cama de gravilla.

Dia 28, 29 de Noviembre

  • Demarcación de estacionamientos.
  • Aseo y entrega.

NOTA: Los trabajos están considerados realizarlos de lunes a viernes en los horarios normales de oficina esto es de 08:30 a 17:30 Hrs.

Cualquier actividad extra o atrasos por imprevistos será avisado oportunamente.