Replacement of gas supply | Reposicion del Suministro de Gas

2018 Jun 7 - 11:45am
Dear all,
We are inform you all, about the replacement of the gas supply system in the Rencinto AURA.
 
The reposition was carried out successfully by the company LAC and the verification of the supply was carried out by Mr. Herman Cuello in each of the houses of the recinto and facilities that were affected.
 
Again the apologies for the inconvenience caused.
 

Estimados,
Junto con saludarlos, se les informa la reposicion del sistema de suministro de gas en recinto AURA.

Cut Gas Supply - Recinto AURA | Corte Suministro de Gas - Recinto AURA

2018 Jun 7 - 9:00am

Dear all,

We are informing you all of a cut of the gas pipe in the upper sector of Recinto AURA, due to the works of ducts, sewer, communication and electricity that is being carried out by the contractor Aniceto Solis; the site is momentarily without gas supply, this will affect the entire site including the residents' homes.

Improvement Upper Gate Road | Mejoramiento Caletera Upper Gate

2018 May 24 - 3:00pm
• I inform you that from this Monday, May 28 th and for a period of approximately 4 days (May 31st) will begin the improvement works of the road access to the Upper Gate, these works will be carried out by the Company SRJ and begin in the section #1 identified in the attached drawing with various improvement works, so, the vehicles parked in the section #2 should be transferred to the already improved (section #1).

Closing of Excavation Area-Drinking water | Cierre Area de Exacavacion-Agua Potable

2018 May 23 - 9:45am
- On Thursday, May 24, 2018 and until June 7, the area indicated in the graph will be closed for pedestrian and vehicular traffic as a result of the excavation works for the installation of drinking water of the new building.
- The vehicular traffic in the area will be carried out by the adjacent road in two directions.
- Drivers must pay attention to the signs of deviation and temporary stoppage of the sector, as well as, to drivers who access climbing to the Recinto to maintain an adequate speed that allows them to be attentive to the conditions of the area.

Wet Network Excavation | Excavacion Red Humeda

2018 May 18 - 4:30pm
- On May 22nd, excavation work will begin in the sector indicated in the image, it aims to install the wet network fire protection of the new building.
- Works will extend until Monday, May 28th, approx.
- Pedestrians are encouraged to respect the segregated areas with cones and danger tape because they are excavations
The vehicles that circulate in the area must maintain a prudent speed in the area, although, a road on the adjacent side to the perimeter closure will not be eliminated, it will be with cones and signs as well as workers in the area.