Modulux Demolition | Demolicion del Modulux

2018 Nov 29 - 10:15am
  • Beginning Thursday, November 29, the Modulux and Motel demolition work will begin.
  • This work will increment the traffic of larger vehicles (trucks) within the Recinto on the roads detailed in image 1.
  • As risk control measures, it has been established that the areas in image 2 must be kept clear of obstacles for the safe transit of trucks. Please respect the no parking sign, cones and warning tape in the area.

Splice work gallery of existing building / Trabajos empalme galeria edificio existente

2018 Nov 7 - 10:30am
  • From tomorrow at 8:00 a.m. until the end of the construction works, the detailed pedestrian access will be closed in graphics for the connection work of the existing building and the new office building.
  • In the area works will be carried out that include excavations and anchoring, therefore the pedestrian crossing is risky.

Dismantling crane tower / Demontaje de Torre Grua

2018 Oct 25 - 5:45am

DESMONTAJE DE GRÚA TORRE CONSTRUCTORA GHG

Fecha de realización de trabajos: viernes 26 y sábado 27 de octubre.

Horario de restricciones:

Viernes 26:

08:00 a 13:00 horas: cerrado el paso a personas y todo tipo de vehículos.

14:00 a 18:00 horas: tránsito peatonal y de vehículos con precaución máxima.

Sábado 27:

08:00 a 13:00 horas: cerrado el paso a personas y todo tipo de vehículos

 


DISMANTLING CRANE TOWER​

Date of work: Friday 26 and Saturday 27 October.

Schedule of restrictions:

Friday 26: