Duct Relocation Work in Progress - Water Cut | Trabajo de Reubicacion de Ductos en Progreso - Corte de Agua

Friday, 24 February 2017 - 2:15pm

Saturday February 25th: There will be a water cut to repair a section located behind the warehouse on the west side of the motel. This work will be done starting at 08:30 hrs and will take approximately 3 hours. The affected areas will be the motel, modulux, warehouse and part of the NOAO administration building.

Monday February 27th: Continuation of the excavation jobs and replacemenet of concrete between the car wash area and instrument workshop.

Tuesday February 28th and onwards: Start of the excavation  work in the east area of the Gemini building (parking lot) to the garden located at the east entrance of the scientific building. Our intention, which has been emphasized on the work we have already done, is to minimize the impact that can be generated in doing this work, therefore, as we move forward, we will enable the areas that will be intervened. 


Sabado 25 de febrero: Corte de agua para efectuar una reparación en el  sector del jardín detrás de la Bodega  y costado oeste del  Motel, trabajo que se realizara a partir de las 08:30 y tendrá una duración de aproximadamente 3 horas, los sectores afectados serán Motel, Modulux, Bodega y la parte este del edificio de administración de NOAO.

Lunes 27 de febrero: Continuación con los trabajos de excavación y reposición de hormigón entre lavadero de autos y taller de instrumentos.

Martes 28 de febrero en adelante: Comienzo con los trabajos de excavación en el sector este del edificio GEMINI (sector estacionamientos) hasta el jardín en la entrada este del edificio científico, nuestra intención como ha sido la tónica en los que ya hemos realizado es minimizar el impacto que se pueda generar al realizarlos, por lo tanto en la medida que iremos avanzando iremos habilitando los sectores que estarán interviniendo.