System Test Plan for the LSST On-sky Commissioning Period

Rubin Observatory is developing a comprehensive plan for the sequence of on-sky and in-dome data acquisition, data processing, and verification activities during the on-sky commissioning period with LSSTCam, considering AOS commissioning, calibration, and science programs together. This session is an opportunity to share updates and collect feedback on the draft test plan.

Agenda:

11:00 – 11:45   Walk-through of current draft system on-sky test plan

11:45 – 12:00   Small-group discussion

12:00 – 12:30   Whole-group discussion

Links:

Zoom

Live notes document

Lead or Chair for this Session: 
Keith Bechtol
Category: 
Commissioning
Systems Engineering
Applicable to: 
Project
Community
Operations
Day: 
Wednesday 08/09

Upload Slides

Please enter the agenda item in the “Subject” field, choose your file, and click save.

Slides