AIV+Commissioning Optimization I
Submitted by cclaver on Fri, 05/10/2019 - 14:59
This is a two session breakout.
We will use the first session to discuss the revised planning for more integrated AIV+Commissioning activities given the pressure on the Project schedule. We will examine at least the following topics:
- Update/Optimization of revised AIV+Commissioning plan/schedule
- Early ComCam integration planning
- On-site logistics
- Establishment of the performance baselines for the environment
Organizer:
Chuck Claver
Day:
Thursday 08/15
Time Block:
11:00am - 12:30pm
Location:
Presidio I